Pipe schedule chart (OD and wall thickness, mm)
| NPS | OD | Sch 10S | Sch 40 | Sch 80 | Sch 160 |
|---|---|---|---|---|---|
| 1/2" | 21.3 | 2.11 | 2.77 | 3.73 | 4.78 |
| 3/4" | 26.7 | 2.11 | 2.87 | 3.91 | 5.56 |
| 1" | 33.4 | 2.77 | 3.38 | 4.55 | 6.35 |
| 1-1/4" | 42.2 | 2.77 | 3.56 | 4.85 | 6.35 |
| 1-1/2" | 48.3 | 2.77 | 3.68 | 5.08 | 7.14 |
| 2" | 60.3 | 2.77 | 3.91 | 5.54 | 8.74 |
| 2-1/2" | 73.0 | 3.05 | 5.16 | 7.01 | 9.53 |
| 3" | 88.9 | 3.05 | 5.49 | 7.62 | 11.13 |
| 4" | 114.3 | 3.05 | 6.02 | 8.56 | 13.49 |
| 6" | 168.3 | 3.4 | 7.11 | 10.97 | 18.26 |
| 8" | 219.1 | 3.76 | 8.18 | 12.7 | 23.01 |
| 10" | 273.1 | 4.19 | 9.27 | 15.09 | 28.58 |
| 12" | 323.9 | 4.57 | 10.31 | 17.48 | 33.32 |
Source: ASME B36.10M and B36.19M. For 12" pipe, Schedule 40S (9.53 mm) is thinner than Schedule 40 (10.31 mm). Read the pipe schedule guide for details.
Frequently asked questions
How is pipe weight per metre calculated?
Weight in kg per metre equals (OD minus wall thickness) multiplied by wall thickness, multiplied by pi and the material density in g/cm³, divided by 1000, with OD and wall in millimetres. For carbon steel this simplifies to (OD − WT) × WT × 0.02466.
Why does stainless steel weigh slightly more than carbon steel?
Austenitic stainless steel has a density of about 7.93 g/cm³ compared with 7.85 g/cm³ for carbon steel, so the same pipe size weighs roughly 1% more.